121 Compensation for loss due to notice

121  Compensation for loss due to notice

(1)     This section applies where—

(a)     an activity specified in a temporary stop notice is, at the time the notice takes effect, authorised by an infrastructure consent order granted before the day the notice takes effect, or

(b)     a relevant planning authority withdraws a temporary stop notice after it has taken effect.

(2)     This section does not apply by virtue of subsection (1)(b) where—

(a)     an activity specified in the temporary stop notice is authorised by an infrastructure consent