20 Effect of requirement for infrastructure consent

20  Effect of requirement for infrastructure consent

(1)     To the extent that infrastructure consent is required for development, none of the following is required for the development—

(a)     planning permission;

(b)     consent under section 36 or 37 of the Electricity Act 1989 (c 29) (construction etc of generating stations and installation of overhead lines);

(c)     authorisation under the following Parts of the Historic Environment (Wales) Act 2023 (asc 3)—

(i)     Part 2 (works affecting scheduled monuments: class authorisations and authorisation by scheduled monument consent);

(ii)     Part 3 (works affecting listed buildings: authorisation by listed building consent);

(iii)