219 Execution and cost of works required by s 215 notice

219  Execution and cost of works required by s 215 notice

(1)     If, within the period specified in a notice under section 215 in accordance with subsection (2) of that section, or within such extended period as the local planning authority who served the notice may allow, any steps required by the notice to be taken have not been taken, the local planning authority who served the notice may—

(a)     enter the land and take those steps, and

(b)     recover from the person who is then the owner of the land any expenses reasonably incurred by them